The
City of Elko has numerous significant improvements planned for the Elko
Regional Airport. Twenty-two million dollars ($23,000,000) is planned
for the Capital Improvement Program at the airport over the next five
(5) years. These improvements include: |
| Project Description: |
Total |
Start Date |
Completion Date |
| Security Improvements/Projects: Phase II |
$450,000 |
2003 |
2003 |
| Construct New Parallel Taxiway for Runway 5-23 and Associated Drainage Improvements |
|
2003 |
2004 |
| Install Runway Surface Sensors |
$360,000 |
2005 |
2005 |
| Upgrade Airfield Lighting |
$117,600 |
2005 |
2005 |
| Construct Air Traffic Control Tower |
$1,050,000 |
2005 |
2006 |
| Acquire CFR Vehicle and Vacuum Truck |
$1,030,000 |
2005 |
2005 |
| Pave Runway 5-23 Shoulders |
$1,060,000 |
2006 |
2007 |
| Extend Runway 5-23 and Taxiway (1,000') including Land Acquisition |
|
2006 |
2007 |
| Expand Commercial and General Aviation Apron |
$3,336,000 |
2007 |
2009 |
| Rehabilitate Airfield Pavements and Overlay Runway 5-23 |
$2,724,000 |
2008 |
2009 |
| Obstruction Removal and Marking |
$287,8000 |
2008 |
2008 |
| Acquire Snowblower (3,000 tons/hr) and Rotary Snowbrooms (2) |
$735,000 |
2008 |
2008 |
| TOTAL |
$23,302,100 |
|
|
*